New Elm Estates Drive road maintenance summary August 2018 through May 2020

Date: 2020-06-12

Our most recent update on the road maintenance was back in August, 2018. We outlined some plans for work by contract to Darrell Naugler and by way of contribution by Ian Goldsmith. We followed that plan and report a few highlights:

Darrell’s work: Shale with Class A build over the outbound section from the end of 2016 work for a distance of about 430 metres (470 yards) at a cost of $19.66/metre ($16.90/yd)

 

Item

Amount

Cost

Class A Gravel

62.69 Tons

$1,247.20

Shale

31 loads

$5,115.00

Machine Time (mini excavator)

10.5 hours

$787.50

Machine time (moving it around)

1 lot

$200.00

Subtotal

 

$7,349.70

Tax (HST)

 

$1,102.46

Total

 

$8,452.16

 

Ian’s work: Concentrated on the gap section between the hill and the pit. This is in lieu of Goldsmith’s (Lot 2) cash contribution for the 2018 year.

Short summary of all work to date over the many years:

 Remaining work to do:

A remaining 2.9 km of road has not been rebuilt including the remainder of New Elm Estates Drive consisting of the gap at the base of the hill and out bound sections to the highway (~1.5 km) and the lake-front section of New Elm Estates Drive to Mint Brook plus Mint Brook and all of Long Cove to the end of all developed lots (~1.4 km).